CDP
Instruction Manual 25
4.3.- OPERATING EXAMPLES FOR THE CDP-G MODEL
4.3.1. SINGLE-PHASE INSTALLATION WITH 1 LOAD TO BE CONNECTED
We start with a single-phase installation in which we want to use the excess
photovoltaic production to supply 1 non-critical load, such as a heat pump.
• Load 1: 5000 W heat pump
The goal is to activate these loads during times in which there is a production
excess, thus reducing energy costs.
This is the baseline data:
Phase P. Inverter Consumption Setpoint Current production
L1 10000 W 4000 W 40% 4000 W (40% of the nominal)
Figure 24: Single-phase installation with 1 load to connect.
The CDP-G programming is shown in Table 11 :